Bethany Lutheran Church
Pictures of Construction at the Stilwell Mission Site

 

A special thanks to Cecil Soeken for providing these pictures.  Check back periodically to see the progress.

 

 Page numbers: Start dates - “linked” to a series of photo pages

P1: 11-02-05

P2: 12-12-05

P3: 01-09-06

P4: 02-13-06

P5: 03-18-06

P6: 04-05-06

 

 

 

 

Click on each small picture to see an Enlarged View

February 13, 2006

February 13, 2006

February 13, 2006

February 13, 2006

West Wall - February 17, 2006

North East Wall - February 17, 2006

West Wall - February 17, 2006

North East Wall - February 17, 2006

Clean-up on March 4, 2006 Clean-up on March 4, 2006
Clean-up on March 4, 2006
Clean-up on March 4, 2006 Sidewalk - South Side of Bldg - March 6, 2006
Clean-up on March 4, 2006 Sidewalk - South Side of Bldg
March 6, 2006
Septic System - March 6, 2006 March 8, 2006
Septic System - March 6, 2006 March 8, 2006

The Septic System has been tested and is now covered up with dirt.  They installed the sidewalk in the front of the church, South side of the building.  The sheetrock is now almost all installed.  They have gotten almost all of the sheetrock mudded in, smooth out, sanded, and ready to paint.  That means we will get to participate in the work load soon.  Are you ready??  The classrooms and office are almost ready.

They are now heating the building with our furnaces.  The ceiling boards arrived this morning, so they are starting to put the ceiling up.  The burm on the East side of the building has been graded and is now ready for us to plant trees.  They are putting the floor in the Scaristy and the NE Storage room off the Chancel area.

Pastor’s Office - March 8, 2006 March 15, 2006
Pastor’s Office - March 8, 2006 March 15, 2006
March 15, 2006 March 18, 2006
March 15, 2006 March 18, 2006